Land reclamation strategy for the Keenleyside Powerplant project : creating opportunity landscapes Baker, Doug; Jackson, J. Leah
Abstract
The Keenleyside Powerplant project requires an estimated 1.9 million cubic meters of material to be excavated over a 6 year period to facilitate the development of a powerhouse and intake structures adjacent to the Keenleyside dam near Castlegar. The excavated material is to be used for both construction purposes and for spoil. A 65 hectare area on the north bank of the Arrow Reservoir, upstream of the Keenleyside dam, has been designated as the spoil site. Much of this area was used for the original construction of the dam in 1972, and was never reclaimed. A progressive, staged reclamation strategy is proposed by B.C. Hydro that identifies opportunity landscapes for recreation and wildlife enhancement along the Arrow reservoir. The spoil material from the powerhouse excavation is sequenced with nine potential areas in which new landscapes can be created. Proposed landscapes include wetland habitat with nature trails, a day-use recreation area, and a beach area. The challenge of the reclamation strategy is to coordinate the removal of materials from the construction site, such that material suitable for construction needs is stockpiled nearby, and spoil material is hauled to designated sites for reclamation. Since the reclaimed sites have specific requirements for soils, the spoil must be sequenced with the specifications of each new landscape. The reclamation strategy is divided into 4 major stages over the construction period that outline the timing of the materials and volumes available for spoil placement. A GIS is used as a data base to model the movement of materials and produce a digital terrain model (DTM) of the desired landscapes. The DTM will also be used as a tool for public input into the project to create final landscape designs for the spoil material.
Item Metadata
Title |
Land reclamation strategy for the Keenleyside Powerplant project : creating opportunity landscapes
|
Creator | |
Contributor | |
Date Issued |
1994
|
Description |
The Keenleyside Powerplant project requires an estimated 1.9 million cubic meters of material to
be excavated over a 6 year period to facilitate the development of a powerhouse and intake
structures adjacent to the Keenleyside dam near Castlegar. The excavated material is to be used for
both construction purposes and for spoil. A 65 hectare area on the north bank of the Arrow
Reservoir, upstream of the Keenleyside dam, has been designated as the spoil site. Much of this
area was used for the original construction of the dam in 1972, and was never reclaimed.
A progressive, staged reclamation strategy is proposed by B.C. Hydro that identifies opportunity
landscapes for recreation and wildlife enhancement along the Arrow reservoir. The spoil material
from the powerhouse excavation is sequenced with nine potential areas in which new landscapes
can be created. Proposed landscapes include wetland habitat with nature trails, a day-use recreation
area, and a beach area.
The challenge of the reclamation strategy is to coordinate the removal of materials from the
construction site, such that material suitable for construction needs is stockpiled nearby, and spoil
material is hauled to designated sites for reclamation. Since the reclaimed sites have specific
requirements for soils, the spoil must be sequenced with the specifications of each new landscape.
The reclamation strategy is divided into 4 major stages over the construction period that outline the
timing of the materials and volumes available for spoil placement.
A GIS is used as a data base to model the movement of materials and produce a digital terrain
model (DTM) of the desired landscapes. The DTM will also be used as a tool for public input into
the project to create final landscape designs for the spoil material.
|
Genre | |
Type | |
Language |
eng
|
Date Available |
2010-02-17
|
Provider |
Vancouver : University of British Columbia Library
|
Rights |
Attribution-NonCommercial-NoDerivatives 4.0 International
|
DOI |
10.14288/1.0042245
|
URI | |
Affiliation | |
Peer Review Status |
Unreviewed
|
Scholarly Level |
Other
|
Copyright Holder |
British Columbia Technical and Research Committee on Reclamation
|
Rights URI | |
Aggregated Source Repository |
DSpace
|
Item Media
Item Citations and Data
Rights
Attribution-NonCommercial-NoDerivatives 4.0 International