- Library Home /
- Search Collections /
- Open Collections /
- Browse Collections /
- UBC Theses and Dissertations /
- A contribution to the study of the performance of steel...
Open Collections
UBC Theses and Dissertations
UBC Theses and Dissertations
A contribution to the study of the performance of steel pipe piles welded to concrete pier cap beams under seismic loads Steunenberg, Mark
Abstract
The Ministry of Transportation and Highways of B.C. implemented a modular bridge program in the Province. In the case of a seismic event, ductility is intended to be achieved through yielding of the steel pipe piles. Each pile has a full strength, overhead weld connecting it to an embedded plate which is cast into the precast concrete abutments and pile caps. The steel piles are intended to undergo plastic hinging; however, a high quality overhead weld is not easy to achieve under adverse site conditions. The performance of the weld under seismic loads is not the only concern. There is limited information on the design of large embedded plates using deformed bar concrete anchors made from deformed wire. This investigation focused on the connection between the steel pile and the concrete cap beam. Two full scale pile segments underwent reversed cyclic loading in order to determine the strength and ductility of the connection. Non-linear, two dimensional modelling and linear, three dimensional finite element modelling was performed. The first specimen failed by the desired plastic hinging. The flail strength weld between the pipe and embedded plate did not fail. The strength and ductility of the connection was as predicted. However, there were initial signs that the deformed anchor bars welded to the embedded plate were debonding. The second specimen was a slightly larger pipe welded to the same concrete beam. The second specimen experienced an embedded plate anchorage failure. The strength and ductility were both well below the desired levels. Although the anchors were longer than the recommended development length, the majority of bars slipped rather than fractured. This slippage led to the low strength and poor ductility. The higher than specified anchor strengths combined with the effects of cyclic loading have been identified as the primary reasons for the disturbing debonding which was observed.
Item Metadata
Title |
A contribution to the study of the performance of steel pipe piles welded to concrete pier cap beams under seismic loads
|
Creator | |
Publisher |
University of British Columbia
|
Date Issued |
1996
|
Description |
The Ministry of Transportation and Highways of B.C. implemented a modular bridge
program in the Province. In the case of a seismic event, ductility is intended to be achieved
through yielding of the steel pipe piles. Each pile has a full strength, overhead weld connecting it
to an embedded plate which is cast into the precast concrete abutments and pile caps. The steel
piles are intended to undergo plastic hinging; however, a high quality overhead weld is not easy to
achieve under adverse site conditions. The performance of the weld under seismic loads is not the
only concern. There is limited information on the design of large embedded plates using deformed
bar concrete anchors made from deformed wire.
This investigation focused on the connection between the steel pile and the concrete cap
beam. Two full scale pile segments underwent reversed cyclic loading in order to determine the
strength and ductility of the connection. Non-linear, two dimensional modelling and linear, three
dimensional finite element modelling was performed.
The first specimen failed by the desired plastic hinging. The flail strength weld between the
pipe and embedded plate did not fail. The strength and ductility of the connection was as
predicted. However, there were initial signs that the deformed anchor bars welded to the
embedded plate were debonding. The second specimen was a slightly larger pipe welded to the
same concrete beam. The second specimen experienced an embedded plate anchorage failure. The
strength and ductility were both well below the desired levels. Although the anchors were longer
than the recommended development length, the majority of bars slipped rather than fractured.
This slippage led to the low strength and poor ductility. The higher than specified anchor
strengths combined with the effects of cyclic loading have been identified as the primary reasons
for the disturbing debonding which was observed.
|
Extent |
13436282 bytes
|
Genre | |
Type | |
File Format |
application/pdf
|
Language |
eng
|
Date Available |
2009-02-06
|
Provider |
Vancouver : University of British Columbia Library
|
Rights |
For non-commercial purposes only, such as research, private study and education. Additional conditions apply, see Terms of Use https://open.library.ubc.ca/terms_of_use.
|
DOI |
10.14288/1.0348362
|
URI | |
Degree | |
Program | |
Affiliation | |
Degree Grantor |
University of British Columbia
|
Graduation Date |
1996-05
|
Campus | |
Scholarly Level |
Graduate
|
Aggregated Source Repository |
DSpace
|
Item Media
Item Citations and Data
Rights
For non-commercial purposes only, such as research, private study and education. Additional conditions apply, see Terms of Use https://open.library.ubc.ca/terms_of_use.