Probabilistic transient stability studies using the BC Hydro system Chia, Timothy Kai-Loh
Abstract
The power utility industry in North America is quickly evolving from a monopolistic environment to a competitive one. Traditional dynamic security assessment methods and tools which have served the industry well in the past cannot provide the risk analysis needed to extract more value out of existing assets. BC Hydro's current deterministic practice is to study the "worst case", where all faults are assumed to be 3$ bus faults with unsuccessful reclosing, at a load factor of 100%. A review of historical fault data from BC Hydro's 500 kV system over the past 20 years has shown these assumptions do not reflect the true nature of the power system. However, they are in place to ensure that minimum operating reliability mandated by regulatory agencies are met. Based on historical statistics, the probabilistic states of load factor, fault type, fault location, fault clearing, and automatic reclosing were applied to a generation rejection study on the Peace system and a transfer limit study on the Columbia system. For each study, 1000 simulations were carried out on a full model of the BC Hydro interconnected system, with the probabilistic states chosen via Monte Carlo techniques. The results were quantified using a BC Hydro developed transient stability assessment module in conjunction with a commercial load flow and dynamic simulation package (PTI's PSS/E). The results showed that BC Hydro's existing deterministic criteria are very conservative, with a risk of instability between 0% and 0.2% in the Peace case and 0.1% in the Columbia case. Although the risk of instability was calculated as 0% for the Peace case, this an approximation error due to the number of samples used. The studies also revealed that the deterministic criteria does not always correspond to the "worst case" as normally assumed. An analysis of the effectiveness of each probabilistic factor considered showed that fault type and successful/unsuccessful reclosing were the more significant factors, while fault location on the line was the least significant. This research has shown that considering the probabilistic nature of the power system in dynamic security assessment can lead to less remedial actions and increased transfer limits.
Item Metadata
Title |
Probabilistic transient stability studies using the BC Hydro system
|
Creator | |
Publisher |
University of British Columbia
|
Date Issued |
1997
|
Description |
The power utility industry in North America is quickly evolving from a
monopolistic environment to a competitive one. Traditional dynamic security assessment
methods and tools which have served the industry well in the past cannot provide the risk
analysis needed to extract more value out of existing assets. BC Hydro's current
deterministic practice is to study the "worst case", where all faults are assumed to be 3$
bus faults with unsuccessful reclosing, at a load factor of 100%. A review of historical
fault data from BC Hydro's 500 kV system over the past 20 years has shown these
assumptions do not reflect the true nature of the power system. However, they are in
place to ensure that minimum operating reliability mandated by regulatory agencies are
met.
Based on historical statistics, the probabilistic states of load factor, fault type,
fault location, fault clearing, and automatic reclosing were applied to a generation
rejection study on the Peace system and a transfer limit study on the Columbia system.
For each study, 1000 simulations were carried out on a full model of the BC Hydro
interconnected system, with the probabilistic states chosen via Monte Carlo techniques.
The results were quantified using a BC Hydro developed transient stability assessment
module in conjunction with a commercial load flow and dynamic simulation package
(PTI's PSS/E).
The results showed that BC Hydro's existing deterministic criteria are very
conservative, with a risk of instability between 0% and 0.2% in the Peace case and 0.1%
in the Columbia case. Although the risk of instability was calculated as 0% for the Peace
case, this an approximation error due to the number of samples used. The studies also
revealed that the deterministic criteria does not always correspond to the "worst case" as
normally assumed.
An analysis of the effectiveness of each probabilistic factor considered showed
that fault type and successful/unsuccessful reclosing were the more significant factors,
while fault location on the line was the least significant. This research has shown that
considering the probabilistic nature of the power system in dynamic security assessment
can lead to less remedial actions and increased transfer limits.
|
Extent |
6018229 bytes
|
Genre | |
Type | |
File Format |
application/pdf
|
Language |
eng
|
Date Available |
2009-03-24
|
Provider |
Vancouver : University of British Columbia Library
|
Rights |
For non-commercial purposes only, such as research, private study and education. Additional conditions apply, see Terms of Use https://open.library.ubc.ca/terms_of_use.
|
DOI |
10.14288/1.0065181
|
URI | |
Degree | |
Program | |
Affiliation | |
Degree Grantor |
University of British Columbia
|
Graduation Date |
1997-11
|
Campus | |
Scholarly Level |
Graduate
|
Aggregated Source Repository |
DSpace
|
Item Media
Item Citations and Data
Rights
For non-commercial purposes only, such as research, private study and education. Additional conditions apply, see Terms of Use https://open.library.ubc.ca/terms_of_use.