KAON Factory study : construction schedule and cost estimate TRIUMF-KAON Project

Abstract

TABLE OF CONTENTS 1 CONSTRUCTION SCHEDULE 1.1 Overall Construction 1.2 Issues at Startup 1.3 Technical and Conventional Construction 2 COST ESTIMATE 2.1 Introduction 2.2 Objectives 2,3 Organization 2.4 Methodology 2.5 Cost Estimate Basis 2.6 Conventional Construction 2.7 Technical Systems 2.8 Engineering, Design, Inspection and Architecture 2.9 Management and Support 2.10 Statement of Accuracy 2.11 Ancillary Project Costs 2.12 . KAON Factory Cost Summaries APPENDICES A. Work Breakdown Structures and Definitions B. Cost Estimate Details